Rewari-Bypass (Haryana)

Construction of proposed Rewari Bypass (NH-11) as Feeder Route in Rewari district in the state of Haryana (Design Length-14.0 km) on Hybrid Annuity Mode (HAM).

State: Haryana

Project Cost: Rs. 522.02 Crores

Length: 14 KMs

Date of PCOD: 25.05.2023

Commissioned under: National Highways Authority of India (NHAI)

Mancherial - Repallewada (Telangana)

Four laning of NH-363 from Mancherial (Design Ch. 0.000/ Existing Km. 251.900) to Repallewada (Design Ch. 42,000/ Existing Km. 288.510) (Design Length = 42 Km) in the State of Telangana under NHDP Phase-IV under NH(0) on Hybrid Annuity mode.

State: Telangana

Project Size: 950.79 Crore

Length: 42 KMs

Date of PCOD: 30.12.2022

Commissioned Under: Adani Road Transport Ltd.

Nandurbar (Kolde) to Khetia PKG-7 (Maharashtra)

Rehabilitation and Upgradation of Nandurbar (Near Kolde) – Prakasha – Sahada - Khetia (SH-4 & SH-5) State Highway from existing Km 50+260 of SH-5, (Kolde) to km 90+220 (Kolde) [Design Ch.50+200 to Km 98+800] to Two Lane with paved shoulders/4 lane in the state of Maharashtra on Engineering, Procurement and Construction (EPC) basis contract.

State: Maharashtra

Length: 48.960 KMs

Date of PCOD: 29.02.2020

Project Size: Rs. 298.11 crore

Commissioned under: PWD Maharashtra

Bhawi - Pipar - Khimsar (Rajasthan)

Development & Up-gradation of Bhawi - Pipar - Khimsar Highway (SH-86C) Length 83.225 Km under RSHDP II (Package No. WB/RSHDP II/EPC 02).

State: Rajasthan

Project Size: Rs. 85.41 crore

Length: 83.225 KMs

Date of PCOD: 04.04.2022

Commissioned under: PWD Rajasthan

Kundal – Jhadol (Udaipur-Rajasthan)

Upgradation to Two Lane with Paved Shoulder configuration from Kundal to Jhadol (Section of NH-58 E), from Km. 0+000 to Km. 43+900 (Design Chainage), Package-I, District-Udaipur in the state of Rajasthan.

State: Rajasthan

Project Size: Rs. 187.11 crore

Length: 58.03 KMs

Date of PCOD: 24.08.2021

Commissioned under: Ministry of Road Transportation & Highways, Government of India

Gurgaon – Sohna

Six Laning and Strengthening of new NH-248A from existing km. 11.682 to existing km. 24.400 in the State of Haryana PKG - 2: Existing Ch. Km 24.400 (Design Ch. Km 9.282 to Km 22.000) under NHDP Phase IV on Hybrid Annuity Mode.

State: Haryana

Date of PCOD: 25.02.2022

Project Size: Rs. 515.00 Crore (Construction /EPC Cost)

Commissioned under: National Highways Authority of India

Hapur – Moradabad

Six laning of Hapur Bypass to Moradabad Section Including Hapur Bypass from km 50.000 to km 149.867 in the State of Uttar Pradesh on DBFOT (Toll) Basis under NHDP Phase-V. (Total Design Length-79.732 Kms).

State: Uttar Pradesh

Date of PCOD: 01.07.2022

Project Size: Rs 972.4 crore

Commissioned under: Modern Road Makers Private Ltd. (A subsidiary of IRB Infrastructure Developers Ltd.)

Jodhpur – Jojawar

Development & Upgradation of Jodhpur -Marwar Junction -Jojawar Highway (SH-61 & 61A) Length 119.095 Km under RSHDP -II Package No.: WB / RSHDP II/ EPC / 03).

State: Rajasthan

Date of PCOD: 15.11.2021

Project Size: Rs. 304.11 crore

Commissioned under: Rajasthan State Highway Development Program - II (RSHDP-II)

Narnaul Bypass

Construction of proposed Narnaul Bypass (design length 24.0 km) and Ateli Mandi to Narnaul Section of NH-11 from km 43.445 to km 56.900 (Design length 14.0km) as an Economic corridor and Feeder Route Package-2 in the state of Haryana on Hybrid Annuity Mode

State: Haryana

Date of PCOD: 11.03.2022

Project Size: Rs. 801.00 Crores (Construction /EPC Cost)

Commissioned under: National Highways Authority of India (NHAI)

Rewari-Ateli Mandi

Upgradation of Four Lane of Rewari-Ateli Mandi section of NH-11 from km 11.780 at Rewari to Ex. Km 43.445 near Ateli Mandi (designed length 30.45 km) as Feeder Route in the state of Haryana on HAM.

State: Haryana

Date of PCOD: 15.11.2021

Project Size: Rs. 488.00 Crore (Construction /EPC Cost)

Commissioned under: National Highways Authority of India (NHAI)

Banar – Kuchera

Development and Upgradation of Banar- Bhopalgarh- Kuchera Highway (SH-63) Km to 126.500 under RSHDP -II (Package No.: WB / RSHDP II/ EPC / 01).

State: Rajasthan

Date of PCOD: 12.04.2021

Project Size: Rs. 207.11 crore

Commissioned under: Rajasthan State Highway Development Program - II (RSHDP-II)

Tonk - Sawai Madhopur

Two Laning with paved shoulder of Tonk- Sawaimadhopur section from Km. 1.300 to Km. 69.750 of NH-116 under NHDP Phase-IV on EPC mode in the State of Rajasthan on EPC mode.

State: Rajasthan

Date of commencement: 18.01.2017

Date of completion: 15.10.2019

Project Size: Rs. 216.11 crore

Commissioned under: National Highways Authority of India (NHAI)

Manoharpur - Dausa

Two laning with paved shoulder of Manoharpur-Dausa section of NH-11 A (New NH-148) from Km 62.100 (Design Ch. 0.000) to Km 0.000 (Design Ch. 62.318) in the State of Rajasthan on EPC mode.

State: Rajasthan

Date of commencement: 20.10.2016

Date of completion: 17.07.2019

Project Size: Rs. 198.21 crore

Commissioned under:National Highways Authority of India(NHAI)

Uncha - Nagla

Nature of work: Widening, strengthening and 2-laning, with paved the shoulder, of the Uncha-Nagla-Khanuawa-Roppas-Dholpur section of NH-123 on an EPC basis.

State: Rajasthan/Uttar Pradesh

Date of commencement: 24.02.2016

Date of completion: 01.10.2019

Project Size: Rs. 261.11 crore

Sitarganj

Two laning with paved shoulders of Sitarganj-Tanakpur section of NH-125 from Km 0.000 (Km 254.600 of NH-74) to Km 52.200 in the state of Uttarakhand under NHDP-IV on EPC mode.

State: Uttarakhand

Date of commencement: 02.09.2015

Date of completion: 20.11.2018

Project Size: Rs. 243.11 crore

Commissioned under: National Highways Authority of India(NHAI)

Yamuna - Expressway

Construction of Earthen EmbanKment , Culverts and Cart Track Underpasses for package A-13 (Km 132.690 to Km 142.740) and construction of Interchange Bridges and Vehicular underpasses for package no B-5 (Km 110.225 to Km 138.00 ), Additional work of Construction of Earthen Embankment, Culverts and Cart Track Underpass Pkg A-15 (b) for Yamuna Expressway.

State: Noida, Uttar Pradesh

Date of completion: 30.06.2012

Project Size: Rs. 116.06 crore

Commissioned under: Jaypee Associates

Kishangarh- Ajmer-Beawar

Six-laning of a stretch of the road (from Km. 364.125 to Km. 58.245) on the Kishangarh-Ajmer-Beawar section of National Highway No. 8.

State: Rajasthan

Date of completion: 08.06.2013

Project Size: Rs. 56.38 crore

Commissioned under: Isolux Corsan India Engineering & Construction Pvt. Ltd.

Sunel - (Jhalawar)

Nature of work: Rehabilitation of Raipur- Mundla- Garwara-Dubliya- Karodiya- Sunel- Sirpoi upto Bhawanimandi Boarder.(MDR-214) Km. 0/0 to 20/0

State: Rajasthan

Date of commencement: 28.08.2017

Date of completion: 27.11.2018

Project Size: Rs. 36.29 crore

Commissioned under: Public Works Department,Divn. -Jhalawar,Rajasthan

In Joint Venture with Ranjit Buildcon

Nature of work: Development and construction to four-laning of the Babatpur – Varanasi section of NH-56

State: Uttar Pradesh

Date of commencement: 15/09/2015

Project Size: Rs 126.93 crore (Our Share)/423.11 Cr(Total Cost)

Commissioned under: MORTH

Agra

Construction of Kuberpur to Fatehabad Road, Agra-Inner Ring Road (Phase-I).

State: Uttar Pradesh

Date of completion: 02.11.2016

Project Size: Rs. 306.95 crore

Commissioned under: Agra Development Authority

Jaipur- Tonk-Deoli

Construction of Four laning of Jaipur - Tonk - Deoli Section of NH- 12 from Km 63 + 000 to Km 114 + 000 (Package no - II).

State: Rajasthan

Date of completion: 25.03.2014

Project Size: Rs. 353.28 crore

Commissioned under: Modern Road makers Pvt. Ltd.(A subsidiary of IRB Infrastructure Developers Ltd.)

Chandrapur

Four Laning of Warora-Chandrapur-Ballarpur-Bamni Road and Bridges on SH-264, part of Warora to Chandrapur from Km. 40.00 to Km. 83.40 part of chandrapur to Bamni from Km. 94.00 to Km. 107.80 including Chandrapur bypass road (SH-266) from Km. 0.00 to Km. 5.20 and 1.20 Km. length of SH 267 in Chandrapur District of Maharashtra State.

State: Maharashtra

Date of completion: 14.08.2013

Project Size: Rs. 268.45 crore

Commissioned under: IL&FS Transportation Networks

Beawar- Pali-Pindwara

Roadworks upto Asphalt from chainage Km. 90.00 to Km. 130.00 for our Beawar-Pali-Pindwara Road Project, NH-14, Rajasthan.

State: Rajasthan

Date of completion: 20.11.2014

Project Size: Rs. 56.33 crore

Commissioned under: L&T ECC, Infra IC

Jaipur - Nagaur

Construction of Jaipur-Nagaur Road Km. 63/500 (Bhatipura) to Km. 101/700 (Narayanpura Tiraha) including Nawa and Mithari Bypass.

State: Rajasthan

Date of completion: 03.03.2014

Project Size: Rs. 47.16 crore

Commissioned under: RSRDC Ltd.

Jaipur - Nagaur

Nature of work: Construction of a segment of the Jaipur-Nagaur Road from Kalwar to Bhatipura

State: Rajasthan

Project Size: Rs. 60.09 crore

Faizabad

Widening and strengthening from Km.0+000 to 46+470 of NH-96 (New NH No.330) in the state of Uttar Pradesh under EPC mode.

State: Uttar Pradesh

Date of completion: 20.10.2016

Project Size: Rs. 171.11 crore

Commissioned under: Ministry of Road Transport and Highways (MoRT&H)

Jaipur - Kishangarh

Second Periodic Renewal Coat on Jaipur-Kishangarh Section of NH-08 (Km. 273.500 to Km. 363.885).

State: Rajasthan

Date of completion: 12.11.2015

Project Size: Rs. 145.11 crore

Commissioned under: GVK Jaipur Expressway Pvt. Ltd

Naraharpur to Kherli

Nature of work: Development of a section of the Badi-Baseri-Bayana-Weir-Bhusawar-Chpkarwada-Kherli and Kherli Bypass road including CD works from Naraharpur to Kherli

State: Rajasthan

Date of completion: 30.10.2014

Project Size: Rs. 58.21 crore

Commissioned under: RSRDC Ltd.

Bharatpur

Development of Road work of Bari-Baseri-Weir-Bhusawar-Chhonkarwara-Kherli-Nagar-Pahari upto Haryana Border Including CD working PKG 01 (Bari to Near Jaisora Km. 0/0 to 23/0).

State: Rajasthan

Date of completion: 15.09.2015

Project Size: Rs. 41.94 crore

Commissioned under: RSRDC Ltd.

Chittorgarh

Strengthening and widening of Hoda Bhadesar Awari Mata Nikumbh Crossing Bari Sadri Bansi Road MDR-182 (Km 0-0 to 59-0) (Total Length 59.00 Km).

State: Rajasthan

Date of completion: 31.05.2017

Project Size: Rs. 46.70 crore

Commissioned under: PWD

Bakani Raipur

Construction of High Level Bridge in Km. 7/0 (Near Bhumada village) with approaches Across River Kali Sindh on Bakani Raipur Pirawa Rampuriya Patpara road upto M. P. Border (MDR 177).

State: Rajasthan

Date of completion: 05.03.2018

Project Size: Rs. 40.69 crore

Commissioned under: PWD

Kaithal

Construction or four laning of Kaithal Rajasthan border section of NH-152/65 from Design Km o+500 to Km. 41-065 (PKG.-lA) in the State of Haryana.

State: Haryana

Date of completion: 04.07.2017

Project Size: Rs. 457.52 crore

Commissioned under: Modern Road makers Pvt. Ltd.(A subsidiary of IRB Infrastructure Developers Ltd.)

Nandagaon - Morshi

Rehabilitation and Upgradation of Amaravati-Nandgaon Peth-Morshi-Warud-Pandhurna Section from Nandgaon Peth to Morshi Section of NH-353K to Two lane with paved shoulders in the state of Maharashtra on Engineering, Procurement & Construction (EPC) Basis Contract

State: Maharashtra

Date of commencement: 13.06.2017

Date of PCOD: 07.11.2019

Project Size: Rs. 243.11 crore

Commissioned under: PWD, NH Division, Nagpur, MORTH

Morshi - Achalpur

Rehabilitation and upgradation of Morshi-Chandurbazar-Achalpur Highway from existing Km 0+000 (Morshi) to Km 53+719 (Achalpur) to two lane with paved shoulders in the state of Maharashtra on EPC basis contract.

State: Maharashtra

Date of commencement: 13.06.2017

Date of PCOD: 15.12.2020

Project Size: Rs. 238.71 crore

Commissioned under: PWD, NH Division, Nagpur, MORTH

Bhandara

Rehabilitation and Upgradation of Bhandara – Khat –Ramtek –Mansar – Mauli – Nayakund –Parseoni – Saoner to joint NH 547 E , PKG – I, Bhandara to Ghotitok, from Km. 166+640 to Km. 205+214 (Design Chainage) to two lane with Paved shoulders/ Four lane configuration in the state of Maharashtra on EPC mode.

State: Maharashtra

Date of commencement: 15.06.2017

Date of PCOD: 31.12.2019

Project Size: Rs. 257.61 crore

Commissioned under: PWD, NH Division, Nagpur, MORTH

Katol - Warud

Rehabilitation and Upgradation of Nagpur-Katol-Warud National Highway from existing Km 60+100 (End of Katol bypass) to 101+085 (Warud up to Joint junction). (Design chainage 60+100 to 100+565) Two lane with paved shoulders in the state of Maharashtra on Engineering, Procurement & Construction (EPC) Basis Contract.

State: Maharashtra

Date of commencement: 12.06.2017

Date of PCOD: 31.01.2020

Project Size: Rs. 314.21 crore

Commissioned under: PWD, NH Division, Nagpur, MORTH

Morshi-Wardhariver

Rehabilitation and Upgradation of two lane with paved shoulder configuration from Morshi to MH/MP border Design Ch. Km. 43.000 to Km. 95.390 Section of National Highway No.353J in the state of Maharashtra on Engineering, Procurement & Construction (EPC) Basis Contract

State: Maharashtra

Date of commencement: 13.06.2017

Date of PCOD: 07.12.2019

Project Size: Rs. 294.51 crore

Commissioned under: PWD, NH Division, Nagpur, MORTH

Amdi Junction to Saoner

Upgradation of NH – 753 Starting from its Junction with NH - 53 near Duggipar connecting Goregaon, Gondia, Tirora, Tumsar, Jam, Ramtek, Parseoni, Khapa and terminating at its Junction with NH -47 near Saoner Section from Amdi Junction to Saoner, PKG–II, from Km. 226+140 to Km. 265+724 (Design Chainage) to two lane with Paved shoulders/ Four lane configuration in the state of Maharashtra on EPC mode.

State: Maharashtra

Date of commencement: 12.06.2017

Date of PCOD: 29.02.2020

Project Size: Rs. 258.33 crore

Commissioned under: PWD, NH Division, Nagpur, MORTH

Balotra

Upgradation to two lane with paved shoulder for section from Km 58.000 to Km 91.600 (excluding Ch (59.460 to 62.900) and (73.120 to 75.920), (82.650 to 85.300) ) Balotra to Sanderao via Jalore section of NH-325 in the State of Rajasthan (PKG-II).

State: Rajasthan

Date of commencement: 20.07.2017

Date of PCOD: 31.12.2019

Project Size: Rs. 113.31 crore

Commissioned under: Ministry of Road Transport and Highways (MoRT&H), Government of Rajasthan

Gulabpura to Chittorgarh

Six Laning of Gulabpura to Chittorgarh section of NH-79 from Design Km 138+870 to Km 213+870 (Package-2) in the state of Rajasthan under NHDP Phase V through Public Private Partnership (PPP) on Design, Built, Operate and Transfer (DBFOT) Toll Basis.

State: Rajasthan

Date of commencement: 03.11.2017

Date of PCOD: 30.06.2021

Project Size: Rs. 711.33 crore

Commissioned under: Modern Road Makers Private Ltd. (A subsidiary of IRB Infrastructure Developers Ltd.)

Delhi - Vadodara (PKG-4)

Completion of 8-lane carriageway starting at Haryana-Rajasthan border, ending at Junction with SH44 (Km 78+800 to Km 115+700) section of Delhi-Vadodara Green Field Alignment (NH-148N) on EPC Mode under Bharatmala Pariyojana (Pkg-4) in the state of Rajasthan.

State: Rajasthan

Date of commencement: 10.12.2019

Date of COD: 26.06.2022

Project Size: Rs. 997.11 Crore

Commissioned under: National Highways Authority of India (NHAI)

Delhi - Vadodara (PKG-8)

Completion of 8-lane access-controlled Expressway starting near start of RoB near junction with NH-11A to junction with MDR-1 (Baonli-Jhalai road) (Ch. 214.260-247.310) section of Delhi – Vadodara Green field Alignment (NH-148N) on EPC Mode under Bharatmala Pariyojana in the State of Rajasthan.

State: Rajasthan

Date of commencement: 07.11.2020

Date of COD: 06.02.2023

Project Size: Rs. 880.11 Crore

Commissioned under: National Highways Authority of India (NHAI)

Chittorgarh - Udaipur

Six Laning of Chittorgarh-Udaipur Section of NH-76 Section-1 from design chainage Ch 214+870 to 263+870 +additional 15Km top layer & RE Wall, Road Furniture, Street Light (Ch.263+870 to 278+870).

State: Rajasthan

Date of commencement: 03.07.2017

Date of PCOD: 13.04.2021

Project Size: Rs. 483.37 crore

Commissioned under: TPL-HGIEPL Joint Venture

GE - Airforce

Nature of work: GE Military Engineering Services

State: Rajasthan

Project Size: Rs. 100.24 crore

Commissioned under: MES

Khonsa section of NH-52B

Nature of Work: Rehabilitation and augmentation of two-laning from the Changlang District Boundary to the Khonsa section of NH-52B. The Arunachal Pradesh package of SARDP_NE on an EPC basis

State: Arunachal Pradesh

Date of commencement: 15/06/2016

Scheduled date of completion: 14/06/2019

Project Size: Rs 100.26 crore (Our Share)/334.22 crore(Total Cost)

Commissioned under: NHIDCL